Steps For Heating And Reforming The Film Blowing Machine
Oct 08, 2018

To remove the original heating ring of the modified part of the barrel.

The size of the barrel is generally measured, generally including the length of the circumference. Calculate the required insulation cotton and estimate whether the position of the winding is sufficient according to the power of the original heating coil.

Wrap the insulation cotton on the barrel and fasten it with a high temperature bandage to keep the thickness of the insulation cotton around 1.5-2.0CM. In order to make the installation more beautiful, a 0.5mm insulating resin can be wrapped on the insulation cotton. board.

The electromagnetic wire is wound on the wrapped barrel, and the wound electromagnetic wire should be as close as possible.

Install an electromagnetic heating control cabinet.